Bullet train: Only one hectare acquired of 1,400 ha required for the massive project

Mahesh Trivedi 30 Oct 2018
Prime Minister Narendra Modi has been shouting from rooftops that the 750-seat, 10-coach, 350-km-an hour train linking India’s financial capital Mumbai with Ahmedabad, the largest city of his home state of Gujarat, will cover the 508-km elevated rail line in two hours flat even after halting at 12 stations and will benefit well-heeled textile traders, diamond merchants and other professionals shuttling between the two metros.

Bullet Train

However, more than a year after it was rolled off, India’s Rs 1.1-trillion ambitious high-speed bullet train project is chugging along at a snail’s pace, with shortage of funds and farmers’ protests now threatening to derail the country’s first cannonball express.

The Japan International Cooperation Agency (JICA), which vowed to bankroll 80% – about Rs 880 billion – of the total cost has so far shelled out the first instalment of only Rs 55 billion, even as Prime Minister Narendra Modi returned from the Land of the Rising Sun on October 29 after a desperate attempt to ensure the second tranche of the 50-year, 0.1% interest soft loan.

Neither the Union Ministry of Railways nor the governments of the two neighboring states controlled by BJP have coughed up a single rupee for his 24-train dream project under which 18 low-noise, aerodynamically-designed trains based on the Shinkansen technology will be imported from Japan while he wants the remaining six trains manufactured under the Make-in-India program.

No wonder, though railway officials are sweating and slaving to complete the project before the 2023 deadline, they now feel that only a 200-km stretch would be made operational by then to keep the promise made to the people.

To add to their woes, Modi, in a bid to make political capital out of the faster and more comfortable high-tech train ahead of the crucial 2019 general elections, advanced the launch date by a year to have it coincide with 75 years of Indian independence on August 15, 2022, saying the crackerjack Indian engineers will pick up the gauntlet.
 

Farmers protest

Meanwhile, 8,000-odd angry farmers and landowners affected by the project have put a spoke in the wheel of the train by refusing to sell their land, demanding a better compensation and complaining about human rights violation and environmental damage, and are bent on soon presenting their gravamina before JICA officials.

After all, the bullet train will pass through 1,400 hectares of land in 312 villages of Gujarat and Maharashtra, take over 866 hectares of fertile farmland, dissect multiple reserved forests, and cut down some 86,000 trees.

Not surprisingly, about 1,200 sons of the soil have submitted affidavits in the Gujarat High Court saying they do not intend to part with their land for the project. Not long ago, ryots from Surat, Valsad and Navsari districts in Gujarat filed 40 more petitions in the same court challenging the process of land acquisition.

What’s more, irate tribals, farmers and fishermen living in hamlets around Maharashtra’s Palghar town near Mumbai on October 28 held out a threat that officials attempting to enter their villages would be tied to trees, sending shivers down the spine of bureaucrats. The result is that the authorities have been able to acquire hardly one hectare of the 1,400 hectares required for the massive project.

While many say that the high-end train will be out of the reach of the masses and will isolate the middle class and poor sections of society, others pointed out that by snatching away prime fertile land, the Modi regime is compromising on the country’s food security.
Senior Congress leader Arjun Modhwadia told this reporter that instead of squandering Rs 1.1 trillion for providing comfort to 4,500 rich commuters, the government should invest the funds for offering better services to the 9,000 million ordinary passengers who travelled by trains every year, adding that evolving technology would cut travel time and obviate the need for acquiring new land.

“The Indian Railways are doing well by speeding up 400 trains in the last four years and converting 120 trains to superfast expresses. So, a bullet train is a wrong priority and a poor country like India does not need one,” he asserted.

Indeed, the growth in domestic air traffic, decrease in jet fuel and improvement in technology have already brought air fares down and the fares for a Mumbai-Ahmedabad flight may go down to below to Rs 3,000, which will be lower than or on a par with the proposed price of Rs 3,000 for the bullet train.

Radheshyam Goswami, a senior journalist and former member of a railway users’ consultative committee, opined that the bullet train was a total waste of money, arguing that by 2023 when the so-called supersonic train would be operational, people would prefer to travel by airplanes with less time and money.

In sum, the National Transport Development Policy Committee had recommended a semi-high speed rail (160-200 kmph) till the time the high-speed rail projects are found commercially justified, and scholars of Indian Institute of Management-Ahmedabad had concluded that 100 daily trips at full occupancy would be required with a fare of Rs 5,000 between Ahmedabad and Mumbai to make the bullet train financially viable.

But an arrogant Modi wanting to talk about the project till he hits the campaign trail next year has decided to wink at these two important suggestions.
---
*Senior Ahmedabad-based journalist. A version of this article first appeared here

Bullet train: Only one hectare acquired of 1,400 ha required for the massive project

Prime Minister Narendra Modi has been shouting from rooftops that the 750-seat, 10-coach, 350-km-an hour train linking India’s financial capital Mumbai with Ahmedabad, the largest city of his home state of Gujarat, will cover the 508-km elevated rail line in two hours flat even after halting at 12 stations and will benefit well-heeled textile traders, diamond merchants and other professionals shuttling between the two metros.

Bullet Train

However, more than a year after it was rolled off, India’s Rs 1.1-trillion ambitious high-speed bullet train project is chugging along at a snail’s pace, with shortage of funds and farmers’ protests now threatening to derail the country’s first cannonball express.

The Japan International Cooperation Agency (JICA), which vowed to bankroll 80% – about Rs 880 billion – of the total cost has so far shelled out the first instalment of only Rs 55 billion, even as Prime Minister Narendra Modi returned from the Land of the Rising Sun on October 29 after a desperate attempt to ensure the second tranche of the 50-year, 0.1% interest soft loan.

Neither the Union Ministry of Railways nor the governments of the two neighboring states controlled by BJP have coughed up a single rupee for his 24-train dream project under which 18 low-noise, aerodynamically-designed trains based on the Shinkansen technology will be imported from Japan while he wants the remaining six trains manufactured under the Make-in-India program.

No wonder, though railway officials are sweating and slaving to complete the project before the 2023 deadline, they now feel that only a 200-km stretch would be made operational by then to keep the promise made to the people.

To add to their woes, Modi, in a bid to make political capital out of the faster and more comfortable high-tech train ahead of the crucial 2019 general elections, advanced the launch date by a year to have it coincide with 75 years of Indian independence on August 15, 2022, saying the crackerjack Indian engineers will pick up the gauntlet.
 

Farmers protest

Meanwhile, 8,000-odd angry farmers and landowners affected by the project have put a spoke in the wheel of the train by refusing to sell their land, demanding a better compensation and complaining about human rights violation and environmental damage, and are bent on soon presenting their gravamina before JICA officials.

After all, the bullet train will pass through 1,400 hectares of land in 312 villages of Gujarat and Maharashtra, take over 866 hectares of fertile farmland, dissect multiple reserved forests, and cut down some 86,000 trees.

Not surprisingly, about 1,200 sons of the soil have submitted affidavits in the Gujarat High Court saying they do not intend to part with their land for the project. Not long ago, ryots from Surat, Valsad and Navsari districts in Gujarat filed 40 more petitions in the same court challenging the process of land acquisition.

What’s more, irate tribals, farmers and fishermen living in hamlets around Maharashtra’s Palghar town near Mumbai on October 28 held out a threat that officials attempting to enter their villages would be tied to trees, sending shivers down the spine of bureaucrats. The result is that the authorities have been able to acquire hardly one hectare of the 1,400 hectares required for the massive project.

While many say that the high-end train will be out of the reach of the masses and will isolate the middle class and poor sections of society, others pointed out that by snatching away prime fertile land, the Modi regime is compromising on the country’s food security.
Senior Congress leader Arjun Modhwadia told this reporter that instead of squandering Rs 1.1 trillion for providing comfort to 4,500 rich commuters, the government should invest the funds for offering better services to the 9,000 million ordinary passengers who travelled by trains every year, adding that evolving technology would cut travel time and obviate the need for acquiring new land.

“The Indian Railways are doing well by speeding up 400 trains in the last four years and converting 120 trains to superfast expresses. So, a bullet train is a wrong priority and a poor country like India does not need one,” he asserted.

Indeed, the growth in domestic air traffic, decrease in jet fuel and improvement in technology have already brought air fares down and the fares for a Mumbai-Ahmedabad flight may go down to below to Rs 3,000, which will be lower than or on a par with the proposed price of Rs 3,000 for the bullet train.

Radheshyam Goswami, a senior journalist and former member of a railway users’ consultative committee, opined that the bullet train was a total waste of money, arguing that by 2023 when the so-called supersonic train would be operational, people would prefer to travel by airplanes with less time and money.

In sum, the National Transport Development Policy Committee had recommended a semi-high speed rail (160-200 kmph) till the time the high-speed rail projects are found commercially justified, and scholars of Indian Institute of Management-Ahmedabad had concluded that 100 daily trips at full occupancy would be required with a fare of Rs 5,000 between Ahmedabad and Mumbai to make the bullet train financially viable.

But an arrogant Modi wanting to talk about the project till he hits the campaign trail next year has decided to wink at these two important suggestions.
---
*Senior Ahmedabad-based journalist. A version of this article first appeared here

Related Articles

Monday

13

Jan

Nationwide

Saturday

04

Jan

Karve Statue, Kothrud, Pune

Theme

Ambedkar

On India's 70th Constitution Day, the Subversive Sangh

Repeated attempts by the RSS-driven Sangh Parivar to appropriate Dr BR Ambedkar throw up contradictions and evasions
JNU

‘Stand by JNU!’ Solidarity Statements from across the world

A campaign launched by the university’s students and teachers challenging the intolerance of dissent
Hindutva

Hindutva and Democracy

Communalism Combat 9th Anniversary Special
HCU

#Stand with HCU

Solidarity Statements and Video Testimonies

Campaigns

Monday

13

Jan

Nationwide

Saturday

04

Jan

Karve Statue, Kothrud, Pune

Videos

Religion

Tales of Bonbibi: The Forest Goddess worshipped by Hindus and Muslims

In times like these, when the political unrest in our country is soaked in communal tension, tales of communal harmony where Hindus and Muslims have worshipped the same Gods and Goddesses since ages, need to be reiterated time and again. Bonbibi or 'Lady of the Forest' is one Goddess that the Hindus and Muslims of Sundarbans, in Bengal, have unanimously prayed to protect themselves from wild animals in the forest, as they ventured inside to collect wood, honey, crabs and fish, thus solidifying the religious syncretism of our country. Watch this video to know more.

Religion

Tales of Bonbibi: The Forest Goddess worshipped by Hindus and Muslims

In times like these, when the political unrest in our country is soaked in communal tension, tales of communal harmony where Hindus and Muslims have worshipped the same Gods and Goddesses since ages, need to be reiterated time and again. Bonbibi or 'Lady of the Forest' is one Goddess that the Hindus and Muslims of Sundarbans, in Bengal, have unanimously prayed to protect themselves from wild animals in the forest, as they ventured inside to collect wood, honey, crabs and fish, thus solidifying the religious syncretism of our country. Watch this video to know more.

Analysis

Ambedkar

On India's 70th Constitution Day, the Subversive Sangh

Repeated attempts by the RSS-driven Sangh Parivar to appropriate Dr BR Ambedkar throw up contradictions and evasions
JNU

‘Stand by JNU!’ Solidarity Statements from across the world

A campaign launched by the university’s students and teachers challenging the intolerance of dissent
Hindutva

Hindutva and Democracy

Communalism Combat 9th Anniversary Special
HCU

#Stand with HCU

Solidarity Statements and Video Testimonies

Archives